top of page

DESIGN SPRINT

5 - DAY PROCESS

Design Sprint - 5 Day Process
MORNING
AFTERNOON
  • Start at the end

  • Map the journey

  • Define the challenge

​

  • Interview experts

  • Producing solution

Design Sprint 2.0 - 5 days in 4

Design Sprint takes up time and for some team members 5 days is just a bit too much in a week to be available. Of course a CEO (or other type of decider with mandate) is the one responsible for strategic and budgetary decisions but he/she does not have to be available throughout the whole of the week. Mostly day 1 and 2 are most important and day 5 is testing day.  

​

If needed the 5 day protocol can also be made to work in 4 days. Where the first two days the presence of key deciders are needed. Day 3 is then about prototyping the chosen solution and day 4 is about testing and getting feedback. This has been designed, tried and tested by the Google Venture team.

Design Sprint extensions

Also, the Design Sprint protocol has been designed and tested in an online version, using Miro, where team members can participate in the comfort of their homes or offices around the world.

​

Finally, the Iteration Sprint is a short 2-3 day 'next steps'-sprint, shortly after the original Design Sprint. It enables for iterating on the Sprint learnings and adapt prototypes for final testing.

bottom of page